Energy grids: from missing link to critical bottleneck in the energy transition
The energy transition has entered a new phase. The challenge is no longer simply generating more renewable electricity. Increasingly, the bottleneck lies in the infrastructure required to transport, balance and store that energy. While investments in solar and wind power continue to grow1, electricity networks are struggling to keep pace. As electrification accelerates across transport, industry and buildings, energy grids are emerging as one of the most critical infrastructure investment themes of the coming decades. To meet rising electricity demand through 2030, annual investment in grid infrastructure will need to grow by approximately 50% from its current level of USD 400 billion. At the same time, grid supply chains must be scaled up and workforce constraints addressed more effectively.2
More renewables require more grids
Renewable energy generation differs fundamentally from conventional power production. Wind farms, especially offshore, solar parks, battery storage facilities and future green hydrogen projects are often located far from population centres and industrial demand hubs. Energy therefore needs to be transported over greater distances and managed more dynamically than in the past.
With the ever increasing renewable generation capacity, transmission and distribution networks must expand and evolve to accommodate intermittent power generation, integrate decentralised energy sources and ensure security of supply. More than 2,500 GW of renewable energy, large-load and storage projects are currently awaiting grid connection worldwide. At the same time, investment in grid infrastructure has failed to keep pace with spending on power generation, leading to growing congestion and increasing levels of renewable curtailment in many electricity systems.3 The rising frequency of negative price periods further signals inefficiencies in electricity markets caused by insufficient network and storage capacity and flexibility.
Without additional investment in electricity grids, charging infrastructure and storage technologies, the energy system will struggle to absorb growing volumes of renewable power.
The challenge is already visible today. Thousands of gigawatts of renewable energy and battery projects are waiting for grid connections around the world, preventing clean energy from being brought online despite being ready for deployment. To address this gap, global grid investment needs to increase substantially over the coming years, with a particular focus on modernising distribution networks, building new transmission lines and strengthening cross-border interconnections.
Capacity of utility-scale battery storage projects in late stages in connection queues in selected countries, 2025
Notes: Late stage refers to battery storage projects at advanced stages of the grid connection process with a high likelihood of completion. Grid connection queue numbers can shift from month to month with project progress, cancellations, and operator reassessments. The figures presented here should therefore be regarded as indicative for 2025. Sources: IEA (2025), Renewables 2025, and IEA analysis based on data from Terna (2025), Bundesnetzagentur (2025), METI (2025), and ESS News (2025).
Source: Electricity 2026.
From traditional grids to smart grids
The grid of the future will look very different from the one built in the twentieth century. Historically, electricity flowed in one direction – from large power plants to consumers. The future energy system will be decentralised, digital and increasingly intelligent.
Millions of distributed assets, including rooftop solar installations, batteries, electric vehicles, heat pumps and small-scale renewable generators, will need to interact seamlessly with the grid – and smart grids will play a central role in this transformation. By leveraging data analytics, sensors and artificial intelligence, smart grids can forecast electricity demand, optimise power flows in real time and improve the integration of renewable energy sources. The deployment of smart meters will be particularly important, as they provide the data foundation required for a more flexible and intelligent electricity system. These capabilities can help maintain grid stability while reducing costs and improving reliability.
Technological innovation is creating entirely new opportunities. Distributed battery storage, local microgrids, long-duration energy storage solutions and demand-side flexibility can all complement traditional network infrastructure and enhance resilience. The result is a more flexible and robust energy system capable of supporting a much larger share of renewable power.
Energy security, competitiveness and economic growth
The modernisation of electricity networks is not only an environmental imperative but also a strategic economic priority. Recent geopolitical developments have highlighted the importance of secure, independent and resilient energy systems. Grid infrastructure can also enhance economic competitiveness. Cross-border interconnectors enable countries to balance supply and demand more efficiently, improve market integration and lower overall system costs. Projects such as NeuConnect, the first submarine electricity interconnector between Germany and the United Kingdom, demonstrate how modern energy infrastructure can increase system flexibility, facilitate renewable integration and strengthen energy cooperation across national borders.
Capturing the Opportunity
According to the European Commission, achieving the EU’s clean energy transition objectives will require around €660 billion of investment per year between 2026 and 2030, increasing to approximately €695 billion annually between 2031 and 2040. And also, transforming energy grids will require enormous amounts of long-term capital. Public funding alone is unlikely to be sufficient, especially given increasing fiscal pressures and competing spending priorities across many countries. Private capital therefore has a crucial role to play
Infrastructure investors are particularly well positioned to support grid modernisation because electricity networks typically exhibit long asset lives, essential-service characteristics and predictable cash-flow profiles. In addition to financing, experienced infrastructure investors can contribute operational expertise, project management capabilities and the ability to mobilise additional institutional capital. Europe alone holds a substantial pool of institutional capital, only a small proportion of which is currently allocated to infrastructure. Increasing these allocations could accelerate the buildout of critical energy infrastructure and help close the investment gap.
Risks and execution challenges
Despite the scale of the opportunity, the path to a modernised grid is not without obstacles. Permitting and planning processes remain a major constraint: depending on the jurisdiction, developing and completing a new transmission line can take between five and fifteen years, far exceeding the timelines needed to keep pace with renewable capacity additions. Regulatory frameworks in many markets have not yet been fully adapted to reflect the urgency of grid expansion, and lengthy approval procedures, land-use conflicts and public acceptance issues can further delay critical projects.
Supply chains present an additional bottleneck. Global demand for transformers, high-voltage cables and other key grid components has risen sharply, leading to extended lead times and, in some cases, multi-year waiting lists for essential equipment. At the same time, the sector faces a shortage of skilled engineers, electricians and project managers capable of designing, building and maintaining increasingly complex and digitalised networks. Without a coordinated effort to expand manufacturing capacity, diversify supply chains and invest in workforce training, these constraints risk slowing the pace of grid build-out even where capital and political will are available. Addressing these execution risks will be just as important as mobilising financing if the energy transition is to stay on track.
Risks and execution challenges
Despite the scale of the opportunity, the path to a modernised grid is not without obstacles. Permitting and planning processes remain a major constraint: depending on the jurisdiction, developing and completing a new transmission line can take between five and fifteen years, far exceeding the timelines needed to keep pace with renewable capacity additions. Regulatory frameworks in many markets have not yet been fully adapted to reflect the urgency of grid expansion, and lengthy approval procedures, land-use conflicts and public acceptance issues can further delay critical projects.
Supply chains present an additional bottleneck. Global demand for transformers, high-voltage cables and other key grid components has risen sharply, leading to extended lead times and, in some cases, multi-year waiting lists for essential equipment. At the same time, the sector faces a shortage of skilled engineers, electricians and project managers capable of designing, building and maintaining increasingly complex and digitalised networks. Without a coordinated effort to expand manufacturing capacity, diversify supply chains and invest in workforce training, these constraints risk slowing the pace of grid build-out even where capital and political will are available. Addressing these execution risks will be just as important as mobilising financing if the energy transition is to stay on track.
Powering the future starts with grids
The energy transition is often associated with wind turbines, solar panels and green hydrogen. Yet none of these technologies can achieve their full potential without modern electricity networks. Energy grids are the backbone of the future energy system. They connect renewable generation with consumers, enable electrification, support energy security and create the foundation for economic competitiveness in a low-carbon economy. As electricity demand continues to rise and power systems become increasingly decentralised, digitalised and interconnected, investment in grid infrastructure will become one of the defining priorities of the energy transition. Simply put: there is no energy transition without energy grids.
Investments of AllianzGI
Allianz Global Investors has been investing in energy infrastructure for more than two decades and has witnessed the sector’s evolution across different market environments and stages of development. This experience provides a useful perspective on the opportunities and challenges associated with the expansion and modernisation of electricity networks, which are becoming increasingly important as power systems electrify and renewable energy capacity grows.
- AllianzGI has invested in NeuConnect, the first direct electricity interconnector between Germany and the United Kingdom. Once operational, the approximately 725-kilometre subsea and land cable connection will enable up to 1.4 GW of electricity to flow in either direction between the two countries, strengthening security of supply and supporting the integration of renewable energy sources. The project illustrates how private capital can help finance critical grid infrastructure that enhances system flexibility and supports Europe’s energy transition.
- The importance of grid infrastructure is also reflected in AllianzGI’s investment in Amprion, Germany’s second-largest transmission system operator. Amprion plays a central role in transporting electricity across the country and enabling the integration of renewable energy sources into the power system. As electricity demand rises and energy systems become more decentralised, investment in electricity networks is increasingly recognised as a prerequisite for energy security, grid resilience and the broader energy transition.
- EsVolta: AllianzGI provided financing for the expansion of esVolta’s battery storage portfolio, providing critical infrastructure supporting grid stability and renewable energy integration across U.S. power markets.
- AMP Clean Energy: AllianzGI backed the development of a 90MWh UK battery storage portfolio, supporting grid stability and the growing share of renewable energy in the power system.
Facts & Figures
Allianz Global Investors has been investing in energy infrastructure for more than two decades and has witnessed the sector’s evolution across different market environments and stages of development. This experience provides a useful perspective on the opportunities and challenges associated with the expansion and modernisation of electricity networks, which are becoming increasingly important as power systems electrify and renewable energy capacity grows.
- More than 2,500 GW of renewable generation, storage and large-load projects are currently stalled in grid connection queues worldwide.4
- Meeting electricity demand through 2030 will require annual grid investment to increase by around 50% from today’s level of USD 400 billion.5
- Planning, permitting and completing new grid infrastructure can take between 5 and 15 years.6
- According to the European Commission, around 120 GW of mature renewable projects, including approximately 1.5 million household installations, risk missing timely grid access by 2030 due to connection bottlenecks.7
- Grid connection queues were present in at least 16 EU Member States as of mid-2026.8
- The IEA estimates that more than 80 million kilometres of power lines will need to be added or refurbished by 2040 to support energy transition objectives.9